Sewer work continues in Ironton

Published 10:26 am Tuesday, June 8, 2010

IRONTON — Ironton’s sewer project will continue this week. Drivers can expect construction zones in several locations in the city including Liberty Avenue and Buckhorn Street between Fifth and Seventh streets.

This week’s schedule for the Ironton sewer project is as follows:

Manhole Cover Replacement

Email newsletter signup

North Ironton between Ellison Street and Center Street

Sewer Cleaning

Third Street alley

Sewer Lining

Liberty Avenue

Buckhorn Street between Fifth Street and Seventh Street

Hecla Street between Fourth Street and Eighth Street

Sixth Street alley between Mill Street and Etna Street

11th Street between Pine Street and Maple Avenue

11th Street alley between Scott Avenue and Vine Street

12th Street alley between Vine Street and Montgomery Street