Sewer work continues this week in Ironton

Published 9:34 am Monday, July 19, 2010

IRONTON — Contractors will be working on the sewer in several areas of Ironton this week as the city’s sewer rehabilitation continues.

The work schedule for the project is as follows:

Manhole Cover Replacement

Email newsletter signup

South Ironton between Walnut Street and Lorain Street

Sewer Lining

Chestnut Street between Third Street and Fifth Street

Elm Street between Fourth Street and Fifth Street

Railroad Street between Fifth Street and Sixth Street

Washington Street between Third Street and Fourth Street

Fourth Street between Mary Street and Vesuvius Street

Fourth Street alley between Vesuvius Street and Hecla Street

Fifth Street between Elm Street and Hawk Street

Fifth Street alley between Mastin Avenue and Kemp Avenue

Eighth Street alley between Vine Street and McGovney Avenue